TAFFYDOME Project - 8.30.2003 - Fabric is on !
We still have quite a bit of work to do however this is a milestone for the project ... in the next few weeks we'll grade the floor with 4-6 inches of crushed stone & sand. __________________________________________________ We have nice pictures from raising the fabric ... We'll load them on the page for documentation of Stage 4 ... Unrolling the fabric and threading pipe required two hours ... Raising the fabric with the three tractors required twenty minutes ... We spent another two hours this day securing the fabric for the next stage ... Our thanks to Sam, Mike, Bill and Dawn ...
|